Planning

Most Recently Approved RTEP Updates
As of 7:20 p.m. EPT

Competitive Planning Process
  • The PJM competitive planning process affords non-incumbent transmission developers an opportunity to participate in the regional planning and expansion of the PJM bulk electric system.
  • 2023 RTEP Window 1
     open7.24.2023 closed9.22.2023
Planning News from Inside Lines
  • PJM, ERCOT, SPP and MISO Join Together on Comments on EPA Emissions Rule
    On August 8, PJM joined MISO, ERCOT and SPP in submitting comments in response to a proposed EPA rule on New Source Performance Standards for Greenhouse Gas Emissions. The geographic reach of the Joint ISOs/RTOs encompasses an area of approximately 2 million square miles, in all or parts of 30 states and the District of […]
  • Board Approves RTEP Updates
    The PJM Board of Managers has authorized changes to the Regional Transmission Expansion Plan (RTEP) to help ensure the most efficient, economical and reliable supply of power for the 65 million people PJM serves across 13 states and the District of Columbia. The updates include two new baseline projects for reliability: Baseline reliability transmission enhancement […]
Queued Generation Fuel Mix
As of 9:20 p.m. EPT
Total:
179,575 MW
Renewables:
92,039 MW
Generation Interconnection Requests by Fuel Type
As of 9:20 p.m. EPT
Queues Timeline
As of 7.13.2023 3:51 p.m. EPT
Criteria & Guidelines